Item 25.1
Labour charge for scraping lawn surface upto 1.5" thick
Considering 1000 sft. of work
(a) Ordinary labour for scraping 1.75 Nos. @ 150 each = 262.5
(b) Ordinary labour for picking-up all sorts of
bricks, bats, rubbish etc. 0.333333333333333 No. @ 150 each = 50
(c) Tools & plant, incidental, sundries etc. L.S. = 24
Total = 336.5
Profit 0.1 = 33.65
Overhead 0.035 = 11.78
= 381.93
Add VAT with adjustment factor 1.04712 0.045 = 18
Grand total = 399.93
Rate per sft. = 0.4
Rate per sqm. = 4.31
Say, 4.3 0 Per sqm