Item 25.2
Preparation of ground to make the scraped lawn fit for plantation
Considering 1000 sft. of work
(a) Labour charge for spading
up to 6" depth 4.5 Nos. @ 150 each = 675
(b) Tools & plant, incidental, sundries etc. L.S. = 37.5
Total = 712.5
Profit 0.1 = 71.25
Overhead 0.035 = 24.94
= 808.69
Add VAT with adjustment factor 1.04712 0.045 = 38.11
Grand total = 846.8
Rate per sft. = 0.85
Rate per sqm. = 9.15
Say, 9 .15 Per sqm.