Item 25.3
Levelling and dressing the lawn areas to proper slope and grade.
Considering 1000 sft. of work
(a) Labour for spading up to 6" depth in/c
cutting earth, levelling-dressing etc. 1.25 Nos. @ 150 each = 187.5
(b) Tools & Plant, sundries, incidental etc. L.S. = 37.5
Total = 225
Profit 0.1 = 22.5
Overhead 0.035 = 7.88
= 255.38
Add VAT with adjustment factor 1.04712 0.045 = 12.03
Grand total = 267.41
Rate per sft. = 0.27
Rate per sqm. = 2.91
Say, 2.9 0 Per sqm.