Item 25.8
Labour charge for mixing cowdung, alluvial loamy silty soil and excavated earth.
Considering 100 cft. of works
(a) Ordinary labour for mixing cowdung,
silty soil & excavated earth 1 No. @ 150 each = 150
(b) Tools & plant, incidental, sundries etc. L.S. = 5
Total = 155
Profit 0.1 = 15.5
Overhead 0.035 = 5.43
= 175.93
Add VAT with adjustment factor 1.04712 0.045 = 8.29
Grand total = 184.22
Rate per cft. = 1.84
Rate per cum. = 64.98
Say, 65 .00 Per cum.