Item 26.26.1
CP soap tray
Considering 1 No. of fixture
(a) CP soap tray 1 No. @ 90 each = 90
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ 4.5 each = 18
(c) Labour:
(i) Plumber 0.025 No. @ 300 each = 7.5
(ii) Skilled labour 0.05 No. @ 200 each = 10
Total = 125.5
Profit 0.1 = 12.55
Overhead 0.035 = 4.39
= 142.44
Add VAT with adjustment factor 1.04712 0.045 = 6.71
Grand total = 149.15
Rate per No. = 149.15
Say, 149 .00 each