Item 26.27
Supplying, fitting-fixing floor-grating of following type:
125 mm dia stainless steel floor-grating
1. 125 mm dia stainless steel grating 1 No. @ 65 each = 65
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ 370 Per bag = 3.7
(ii) Sand (F.M. 1.2) 0.05 cft. @ 1300 Per % cft. = 0.65
3. Labour:
(a) Skilled labour 0.15 No. @ 200 each = 30
Total = 99.35
Profit 0.1 = 9.94
Overhead 0.035 = 3.48
= 112.77
Add VAT with adjustment factor 1.04712 0.045 = 5.31
Grand total = 118.08
Rate per No. = 118.08
Say, 118 .00 each