Item 26.28
62 mm dia stainless steel floor-grating
Considering 1 No. of fixture
1. 62 mm dia stainless steel grating 1 No. @ 50 each = 50
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ 370 Per bag = 3.7
(ii) Sand (F.M. 1.2) 0.05 cft. @ 1300 Per % cft. = 0.65
3. Labour:
(a) Skilled labour 0.1 No. @ 200 each = 20
Total = 74.35
Profit 0.1 = 7.44
Overhead 0.035 = 2.6
= 84.39
Add VAT with adjustment factor 1.04712 0.045 = 3.98
Grand total = 88.37
Rate per No. = 88.37
Say, 88 .00 each