Item 26.32
Supplying, fitting & fixing of soil, waste and ventilation pipe of following type (cement mortar jointing)
50 mm dia HCI, single hub pipe
Considering 3 x 1.83 m= 5.49 meter work
(a) 50 mm dia 1.8 m long HCI pipe: 3 Nos. @ 750 each = 2250
(b) Fittings:
(i) Bend/45O bend/ off-set/cowel etc. 1 No. @ 163 each = 163
(ii) Tee/T-Y/Y(50 x 50 mm) 1 No. @ 550 each = 550
(c) Jointing & fixing materials
(i) Hem 25 gm. @ 1 Per gm. = 25
(ii) Cement 0.02 bag. @ 370 Per bag. = 7.4
(iii) Sand (F.M. 1.2) 0.05 cft. @ 1300 Per % cft. = 0.65
(iv) Clamp 3 Nos. @ 27.36 each = 82.08
(v) Rowel plug & screw 6 Nos. @ 16 each = 96
(vi) Scaffolding 18 rft. @ 1 Per rft. = 18
(d) Labour:
(i) Plumber 0.1 No. @ 300 each = 30
(ii) Skilled labour 0.2 No. @ 200 each = 40
(iii) Ordinary labour 0.4 No. @ 150 each = 60
Total = 3322.13
Profit 0.1 = 332.21
Overhead 0.035 = 116.27
= 3770.61
Add VAT with adjustment factor 1.04712 0.045 = 177.67
Grand total = 3948.28
Rate per rm. = 719.18
Say, 719 .00 Per rm