Item 26.33
100 mm dia HCI, single hub pipe
Considering 3 x 1.83 m= 5.49 meter work
(a) 100 mm dia 1.83 m long HCI pipe: 3 Nos. @ 1500 each = 4500
(b) Fittings:
(i) Bend/45O bend/off-set/cowel etc. 1 No. @ 344 each = 344
(ii) Tee/T-Y/Y(100 x 100/50 mm) 1 No. @ 650 each = 650
(c) Jointing & fixing materials
(i) Hem 50 gm. @ 1 Per gm. = 50
(ii) Cement 0.04 bag. @ 370 Per bag. = 14.8
(iii) Sand (F.M. 1.2) 0.1 cft. @ 1300 Per % cft. = 1.3
(iv) Clamp 3 Nos. @ 36.48 each = 109.44
(v) Rowel plug & screw 6 Nos. @ 16 each = 96
(vi) Scaffolding 18 rft. @ 1 Per rft. = 18
(d) Labour:
(i) Plumber 0.3 No. @ 300 each = 90
(ii) Skilled labour 0.6 No. @ 200 each = 120
(iii) Ordinary labour 0.12 No. @ 150 each = 18
Total = 6011.54
Profit 0.1 = 601.15
Overhead 0.035 = 210.4
= 6823.09
Add VAT with adjustment factor 1.04712 0.045 = 321.51
Grand total = 7144.6
Rate per rm. = 1301.38
Say, 1301 .00 Per rm