Item 26.34
150 mm diaHCI, single hub pipe
Considering 3 x 1.83 m = 5.49 meter work
(a) 150 mm dia 1.8 m long HCI pipe: 3 Nos. @ 2250 each = 6750
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 No. @ 850 each = 850
(ii) Tee/T-Y/Y 1 No. @ 1125 each = 1125
(c) Jointing & fixing materials
(i) Hem 75 gm. @ 1 Per gm. = 75
(ii) Cement 0.06 bag. @ 370 Per bag. = 22.2
(iii) Sand (F.M. 1.2) 0.3 cft. @ 1300 Per % cft. = 3.9
(iv) Clamp 3 Nos. @ 45.6 each = 136.8
(v) Rowel plug & screw 6 Nos. @ 20 each = 120
(vi) Scaffolding 36 rft. @ 1 Per rft. = 36
(d) Labour:
(i) Plumber 0.3 No. @ 300 each = 90
(ii) Skilled labour 0.6 No. @ 200 each = 120
(iii) Ordinary labour 0.12 No. @ 150 each = 18
Total = 9346.9
Profit 0.1 = 934.69
Overhead 0.035 = 327.14
= 10608.73
Add VAT with adjustment factor 1.04712 0.045 = 499.89
Grand total = 11108.62
Rate per rm. = 2023.43
Say, 2023 .00 Per rm