Item 26.39.2
Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia uPVC pipe 70 rft. @ 18 Per rft. = 1260
(b) Fittings:
(i) 19 mm uPVC plain Tee 5 Nos. @ 19 each = 95
(ii) 19 mm uPVC plain elbow 10 Nos. @ 15 each = 150
(iii) 19 mm uPVC plain socket 4 Nos. @ 10 each = 40
(iv) 19 x 12 mm uPVC round Tee 5 Nos. @ 22 each = 110
(v) 19 x 12 mm uPVC round elbow 10 Nos. @ 24 each = 240
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ 1 Per gm. = 50
(d) Labour:
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
(iii) Labour 1 No. @ 150 each = 150
Total = 2595
Profit 0.1 = 259.5
Overhead 0.035 = 90.83
= 2945.33
Add VAT with adjustment factor 1.04712 0.045 = 138.79
Grand total = 3084.12
Rate per rft. = 44.06
Rate per rm. = 144.56
Say, 145 .00 Per rm