Item 26.40.2
Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia CPVC pipe 70 rft. @ 35.07 Per rft. = 2454.9
(b) Fittings:
(i) 19 mm CPVC plain Tee 5 Nos. @ 53.8 each = 269
(ii) 19 mm CPVC plain elbow 10 Nos. @ 37.34 each = 373.4
(iii) 19 mm CPVC plain socket 4 Nos. @ 24.69 each = 98.76
(iv) 19 x 12 mm CPVC round Tee 5 Nos. @ 46.37 each = 231.85
(v) 19 x 12 mm CPVC round elbow 10 Nos. @ 74.86 each = 748.6
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ 1 Per gm. = 50
(d) Labour:
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
(iii) Labour 1 No. @ 150 each = 150
Total = 4876.51
Profit 0.1 = 487.65
Overhead 0.035 = 170.68
= 5534.84
Add VAT with adjustment factor 1.04712 0.045 = 260.8
Grand total = 5795.64
Rate per rft. = 82.79
Rate per rm. = 271.63
Say, 272 .00 Per rm