Item 26.41.2
Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia ABS pipe 70 rft. @ 51.6 Per rft. = 3612
(b) Fittings:
(i) 19 mm ABS plain Tee 5 Nos. @ 67.74 each = 338.7
(ii) 19 mm ABS plain elbow 10 Nos. @ 47.09 each = 470.9
(iii) 19 mm ABS plain socket 4 Nos. @ 31.05 each = 124.2
(iv) 19 x 12 mm ABS round Tee 5 Nos. @ 17.23 each = 86.15
(v) 19 x 12 mm ABS round elbow 10 Nos. @ 112.1 each = 1121
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 50 gm. @ 2 Per gm. = 100
(d) Labour:
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
(iii) Labour 1 No. @ 150 each = 150
Total = 6502.95
Profit 0.1 = 650.3
Overhead 0.035 = 227.6
= 7380.85
Add VAT with adjustment factor 1.04712 0.045 = 347.79
Grand total = 7728.64
Rate per rft. = 110.41
Rate per rm. = 362.26
Say, 362 .00 Per rm