Item 26.43.2
Considering 20 rft. long 1 No. pipe
(a) 150 mm dia 20'-0" long uPVC pipe: 20 rft. @ 125 Per rft. = 2500
(b) Jointing materials
(i) Solvent cement 120 gm @ 1 Per gm. = 120
(c) Excavation 72.04 cft. @ 1412.5 Per % 0 cft. = 101.76
(d) Bedding by sand (F.M. 1.2) 12.36 cft. @ 1300 Per cft. = 160.68
(e) Labour:
(i) Plumber 0.25 No. @ 300 each = 75
(ii) Skilled labour 0.5 No. @ 200 each = 100
(iii) Ordinary labour 0.5 No. @ 150 each = 75
Total = 3132.44
Profit 0.1 = 313.24
Overhead 0.035 = 109.64
= 3555.32
Add VAT with adjustment factor 1.04712 0.045 = 167.53
Grand total = 3722.85
Rate per rft. = 186.14
Rate Per rm. = 610.73
Say, 611 .00 Per rm