Item 26.46.2
Considering 20 rft. long one pipe
(a) 200 mm uPVC pipe: 20 rft. @ 200 Per rft. = 4000
(b) Jointing materials
(i) Solvent cement 50 gm @ 1 Per gm. = 50
(c) Excavation 87.5 cft. @ 1412.5 Per % 0 cft. = 123.59
(d) Bedding by sand (F.M. 0.8) 67.5 cft. @ 1133.75 Per cft. = 765.28
(e) Labour:
(i) Plumber 0.25 No. @ 300 each = 75
(ii) Skilled labour 0.5 No. @ 200 each = 100
(iii) Ordinary labour 0.5 No. @ 150 each = 75
Total = 5188.87
Profit 0.1 = 518.89
Overhead 0.035 = 181.61
= 5889.37
Add VAT with adjustment factor 1.04712 0.045 = 277.51
Grand total = 6166.88
Rate per rft. = 308.34
Rate Per rm. = 1011.66
Say, 1012 .00 Per rm