Item 26.46.4
Considering 20 rft. long one pipe
(a) 280 mm uPVC pipe: 20 rft. @ 400 Per rft. = 8000
(b) Jointing materials
(i) Solvent cement 330 gm @ 1 Per gm. = 330
(c) Excavation 87.5 cft. @ 1412.5 Per % 0 cft. = 123.59
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ 1133.75 Per cft. = 595.22
(e) Labour:
(i) Plumber 0.25 No. @ 300 each = 75
(ii) Skilled labour 0.5 No. @ 200 each = 100
(iii) Ordinary labour 1 No. @ 150 each = 150
Total = 9373.81
Profit 0.1 = 937.38
Overhead 0.035 = 328.08
= 10639.27
Add VAT with adjustment factor 1.04712 0.045 = 501.33
Grand total = 11140.6
Rate per rft. = 557.03
Rate Per rm. = 1827.62
Say, 1828 .00 Per rm