Item 26.46.5
Considering 20 rft. long one pipe
(a) 315 mm uPVC pipe: 20 rft. @ 520 Per rft. = 10400
(b) Jointing materials
(i) Solvent cement 330 gm @ 1 Per gm. = 330
(c) Excavation 87.5 cft. @ 1412.5 Per % 0 cft. = 123.59
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ 1133.75 Per cft. = 595.22
(e) Labour:
(i) Plumber 0.25 No. @ 300 each = 75
(ii) Skilled labour 0.5 No. @ 200 each = 100
(iii) Ordinary labour 1 No. @ 150 each = 150
Total = 11773.81
Profit 0.1 = 1177.38
Overhead 0.035 = 412.08
= 13363.27
Add VAT with adjustment factor 1.04712 0.045 = 629.68
Grand total = 13992.95
Rate per rft. = 699.65
Rate Per rm. = 2295.55
Say, 2296 .00 Per rm
Card image cap
Card title

This is a wider card with supporting text below as a natural lead-in to additional content. This content is a little bit longer.

Last updated 3 mins ago