Item 26.48.5
Considering 1 No. of fixture
(a) 40 mm dia Gate Valve 1 No. @ 500 each = 500
(b) Fitting fixing materials:
(i) Teflon tape 1.58 rft. @ 1 Per rft. = 1.58
(c) Labour:
(i) Plumber 0.06 No. @ 300 each = 18
(ii) Skilled labour 0.11 No. @ 200 each = 22
(iii) Ordinary labour 0.2 No. @ 150 each = 30
Total = 571.58
Profit 0.1 = 57.16
Overhead 0.035 = 20.01
= 648.75
Add VAT with adjustment factor 1.04712 0.045 = 30.57
Grand total = 679.32
Rate per No. = 679.32
Say, 679 .00 each