Item 26.48.8
Considering 1 No. of fixture
(a) 75 mm dia Gate Valve 1 No. @ 2100 each = 2100
(b) Fitting fixing materials:
(i) Teflon tape 3.13 rft. @ 1 Per rft. = 3.13
(c) Labour:
(i) Plumber 0.1 No. @ 300 each = 30
(ii) Skilled labour 0.175 No. @ 200 each = 35
(iii) Ordinary labour 0.2 No. @ 150 each = 30
Total = 2198.13
Profit 0.1 = 219.81
Overhead 0.035 = 76.93
= 2494.87
Add VAT with adjustment factor 1.04712 0.045 = 117.56
Grand total = 2612.43
Rate per No. = 2612.43
Say, 2612 .00 each