Item 26.52.2
Considering 1 No. of fixture
1. 100 x 100 or 100 x 50 mm
dia HCI Y or T-Y 1 No. @ 600 each = 600
2. Jointing materials
(a) Hem 100 gm. @ 1 Per gm. = 100
(b) Cement mortar (1:4)
(i) Cement 0.016 bag. @ 370 Per bag. = 5.92
(ii) Sand (F.M. 1.2) 0.04 cft. @ 1300 Per % cft. = 0.52
3. Labour:
(a) Plumber 0.05 No. @ 300 each = 15
(b) Skilled labour 0.1 No. @ 200 each = 20
(c) Ordinary labour 0.19 No. @ 150 each = 28.5
Total = 769.94
Profit 0.1 = 76.99
Overhead 0.035 = 26.95
= 873.88
Add VAT with adjustment factor 1.04712 0.045 = 41.18
Grand total = 915.06
Rate per No. = 915.06
Say, 915 .00 each