Item 26.52.3
Considering 1 No. of fixture
1. 100 x 100 or 150 x 100 mm dia
HCI Y or T-Y cleanout 1 No. @ 900 each = 900
2. ii. Cost of jointing
(a) Hem 50 gm. @ 1 Per gm. = 50
(b) Cement mortar (1:4)
(i) Cement 0.008 bag. @ 370 Per bag. = 2.96
(ii) Sand (F.M. 1.2) 0.02 cft. @ 1300 Per % cft. = 0.26
3. Labour:
(a) Plumber 0.03 No. @ 300 each = 9
(b) Skilled labour 0.07 No. @ 200 each = 14
(c) Ordinary labour 0.162 No. @ 150 each = 24.3
Total = 1000.52
Profit 0.1 = 100.05
Overhead 0.035 = 35.02
= 1135.59
Add VAT with adjustment factor 1.04712 0.045 = 53.51
Grand total = 1189.1
Rate per No. = 1189.1
Say, 1189 .00 each