Item 26.52.4
Considering 1 No. of fixture
1. 50 mm dia HCI trap 1 No. @ 370 each = 370
2. Jointing materials
(a) Hem 25 gm. @ 1 Per gm. = 25
(b) Cement mortar (1:4)
(i) Cement 0.004 bag. @ 370 Per bag. = 1.48
(ii) Sand (F.M. 1.2) 0.01 cft. @ 1300 Per % cft. = 0.13
3. Labour:
(a) Plumber 0.025 No. @ 300 each = 7.5
(b) Skilled labour 0.05 No. @ 200 each = 10
(c) Ordinary labour 0.095 No. @ 150 each = 14.25
Total = 428.36
Profit 0.1 = 42.84
Overhead 0.035 = 14.99
= 486.19
Add VAT with adjustment factor 1.04712 0.045 = 22.91
Grand total = 509.1
Rate per No. = 509.1
Say, 509 .00 each