Item 26.53.2
Considering 1 No. of fixture
(a) 100 mm dia plastic trap 1 No. @ 300 each = 300
(b) Jointing materials
(i) Solvent cement 27 gm. @ 1 Per gm. = 27
(c) Labour:
(i) Plumber 0.03 No. @ 300 each = 9
(ii) Skilled labour 0.07 No. @ 200 each = 14
(iii) Ordinary labour 0.162 No. @ 150 each = 24.3
Total = 374.3
Profit 0.1 = 37.43
Overhead 0.035 = 13.1
= 424.83
Add VAT with adjustment factor 1.04712 0.045 = 20.02
Grand total = 444.85
Rate per No. = 444.85
Say, 445 .00 each