Item 26.53.3
Considering 1 No. of fixture
(a) 100 mm dia plastic
Y or "T-Y" cleanout 1 No. @ 350 each = 350
(b) Jointing Materials
(i) Solvent cement 27 gm. @ 1 Per gm. = 27
(c) Labour:
(i) Plumber 0.045 No. @ 300 each = 13.5
(ii) Skilled labour 0.09 No. @ 200 each = 18
(iii) Ordinary labour 0.161 No. @ 150 each = 24.15
Total = 432.65
Profit 0.1 = 43.27
Overhead 0.035 = 15.14
= 491.06
Add VAT with adjustment factor 1.04712 0.045 = 23.14
Grand total = 514.2
Rate per No. = 514.2
Say, 514 .00 each