Item 26.53.4
Considering 1 No. of fixture
(a) 50 mm dia plastic trap 1 No. @ 300 each = 300
(b) Jointing materials
(i) Solvent cement 10 gm. @ 1 Per gm. = 10
(c) Labour:
(i) Plumber 0.025 No. @ 300 each = 7.5
(ii) Skilled labour 0.05 No. @ 200 each = 10
(iii) Ordinary labour 0.095 No. @ 150 each = 14.25
Total = 341.75
Profit 0.1 = 34.18
Overhead 0.035 = 11.96
= 387.89
Add VAT with adjustment factor 1.04712 0.045 = 18.28
Grand total = 406.17
Rate per No. = 406.17
Say, 406 .00 each