Item 26.55.2
Considering 1 No. of fixture
(a) 12 mm CP heavy duty pillar cock 1 No. @ 600 each = 600
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ 1 Per rft. = 0.3
(c) Labour:
(i) Plumber 0.025 No. @ 300 each = 7.5
(ii) Skilled labour 0.05 No. @ 200 each = 10
(iii) Ordinary labour 0.095 No. @ 150 each = 14.25
Total = 632.05
Profit 0.1 = 63.21
Overhead 0.035 = 22.12
= 717.38
Add VAT with adjustment factor 1.04712 0.045 = 33.8
Grand total = 751.18
Rate per No. = 751.18
Say, 751 .00 each