Item 26.57.1
CP basin mixture
Considering 1 No. of fixture
(a) CP basin mixture 1 No. @ 1400 each = 1400
(b) Fitting-fixing materials
(i) Teflon tape 0.04 rft. @ 1 Per rft. = 0.04
(c) Labour:
(i) Plumber 0.06 No. @ 300 each = 18
(ii) Skilled labour 0.12 No. @ 200 each = 24
(iii) Ordinary labour 0.248 No. @ 150 each = 37.2
Total = 1479.24
Profit 0.1 = 147.92
Overhead 0.035 = 51.77
= 1678.93
Add VAT with adjustment factor 1.04712 0.045 = 79.11
Grand total = 1758.04
Rate per No. = 1758.04
Say, 1758 .00 each