Item 26.58
CP shower mixture in/c shower head only
Considering 1 No. of fixture
(a) CP shower mixture 1 No. @ 2000 each = 2000
(b) Fitting-fixing materials
(i) Teflon tape 0.5 rft. @ 1 Per rft. = 0.5
(c) Labour:
(i) Plumber 0.09 No. @ 300 each = 27
(ii) Skilled labour 0.156 No. @ 200 each = 31.2
(iii) Ordinary labour 0.4 No. @ 150 each = 60
Total = 2118.7
Profit 0.1 = 211.87
Overhead 0.035 = 74.15
= 2404.72
Add VAT with adjustment factor 1.04712 0.045 = 113.31
Grand total = 2518.03
Rate per No. = 2518.03
Say, 2518 .00 each