Item 26.60
CP bath-tub mixture with shower head only
Considering 1 No. of fixture
(a) CP bath-tub mixture 1 No. @ 3500 each = 3500
(b) Fitting-fixing materials
(i) Teflon tape 0.5 rft. @ 1 Per rft. = 0.5
(c) Labour:
(i) Plumber 0.09 No. @ 300 each = 27
(ii) Skilled labour 0.156 No. @ 200 each = 31.2
(iii) Ordinary labour 0.4 No. @ 150 each = 60
Total = 3618.7
Profit 0.1 = 361.87
Overhead 0.035 = 126.65
= 4107.22
Add VAT with adjustment factor 1.04712 0.045 = 193.53
Grand total = 4300.75
Rate per No. = 4300.75
Say, 4301 .00 each