Item 26.64.2
Considering 3 meter long groove
(a) Labour for cutting and filling groove
(i) Plumber 0.09 No. @ 300 each = 27
(ii) Skilled labour 0.156 No. @ 200 each = 31.2
(iii) Ordinary labour 0.4 No. @ 150 each = 60
(b) Cement mortar (1:4)
(i) Cement 0.1 bag @ 370 Per bag = 37
(ii) Sand (F.M. 1.2) 0.5 cft. @ 1300 Per % cft. = 6.5
Total = 118.2
Profit 0.1 = 11.82
Overhead 0.035 = 4.14
= 134.16
Add VAT with adjustment factor 1.04712 0.045 = 6.32
Grand total = 140.48
Rate per rm. = 46.83
Say, 47 .00 Per rm.