Item 26.65.2
Considering 1 No. of fixture
(a) Moving type 100 mm CP
cleanging shower rose 1 No. @ 500 each = 500
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ 1 Per rft. = 0.3
(ii) Rowel plug & screw 4 Nos. @ 4 each = 16
(c) Labour:
(i) Plumber 0.115 No. @ 300 each = 34.5
(ii) Skilled labour 0.19 No. @ 200 each = 38
(iii) Ordinary labour 0.225 No. @ 150 each = 33.75
Total = 622.55
Profit 0.1 = 62.26
Overhead 0.035 = 21.79
= 706.6
Add VAT with adjustment factor 1.04712 0.045 = 33.3
Grand total = 739.9
Rate per No. = 739.9
Say, 740 .00 each