Item 26.66.2
Considering 1 No. of fixture
(a) Moving type 100 mm
CP shower rose 1 No. @ 450 each = 450
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ 1 Per rft. = 0.3
(c) Labour:
(i) Plumber 0.03 No. @ 300 each = 9
(ii) Skilled labour 0.06 No. @ 200 each = 12
(iii) Ordinary labour 0.124 No. @ 150 each = 18.6
Total = 489.9
Profit 0.1 = 48.99
Overhead 0.035 = 17.15
= 556.04
Add VAT with adjustment factor 1.04712 0.045 = 26.2
Grand total = 582.24
Rate per No. = 582.24
Say, 582 .00 each