Item 26.67.2
Considering 1 No. of fixture
(a) 1500 liter water-tank 1 No. @ 14250 each = 14250
(b) Carrying up to site L.S. = 187.5
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ 1 Per rft. = 4.2
(ii) Nipple with jam-nuts 4 Nos. @ 44 each = 176
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
(iii) Ordinary labour 1 No. @ 150 each = 150
Total = 15267.7
Profit 0.1 = 1526.77
Overhead 0.035 = 534.37
= 17328.84
Add VAT with adjustment factor 1.04712 0.045 = 816.54
Grand total = 18145.38
Rate per No. = 18145.38
Say, 18145 .00 each