Item 26.67.3
Considering 1 No. of fixture
(a) 2000 liter water-tank 1 No. @ 19000 each = 19000
(b) Carrying up to site L.S. = 225
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ 1 Per rft. = 4.2
(ii) Nipple with jam-nuts 4 Nos. @ 44 each = 176
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
(iii) Ordinary labour 2 No. @ 150 each = 300
Total = 20205.2
Profit 0.1 = 2020.52
Overhead 0.035 = 707.18
= 22932.9
Add VAT with adjustment factor 1.04712 0.045 = 1080.61
Grand total = 24013.51
Rate per No. = 24013.51
Say, 24014 .00 each