Item 26.68.2
emergency storage and supply of water: 300 liter capacity
Considering 1 No. of fixture
(a) 300 literplastic water tank 1 No. @ 3600 each = 3600
(b) Carrying up to site L.S. = 112.5
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ 1 Per rft. = 4.2
(ii) 3/4" dia ball cock 1 No. @ 180 each = 180
(iii) Nipple with jam-nuts 1 No. @ 95 each = 95
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 1 No. @ 200 each = 200
Total = 4491.7
Profit 0.1 = 449.17
Overhead 0.035 = 157.21
= 5098.08
Add VAT with adjustment factor 1.04712 0.045 = 240.22
Grand total = 5338.3
Rate per No. = 5338.3
Say, 5338 .00 each