Item 26.69.2
Considering 1 No. of fixture
(a) 1000 liter stainless steel water tank 1 No. @ 11500 each = 11500
(b) Carrying up to site L.S. = 112.5
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 No. @ 180 Per rft. = 180
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ 64.5 each = 64.5
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = 150
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ 300 each = 300
(ii) Skilled labour 2 Nos. @ 200 each = 400
Total = 12707
Profit 0.1 = 1270.7
Overhead 0.035 = 444.75
= 14422.45
Add VAT with adjustment factor 1.04712 0.045 = 679.59
Grand total = 15102.04
Rate per No. = 15102.04
Say, 15102 .00 each