Item 26.69.3
Considering 1 No. of fixture
(a) 2000 liter stainless steel water tank 1 No. @ 20100 each = 20100
(b) Carrying L.S. = 225
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ 180 Per rft. = 180
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ 64.5 each = 64.5
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = 225
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1.5 No. @ 300 each = 450
(ii) Skilled labour 3 Nos. @ 200 each = 600
Total = 21844.5
Profit 0.1 = 2184.45
Overhead 0.035 = 764.56
= 24793.51
Add VAT with adjustment factor 1.04712 0.045 = 1168.28
Grand total = 25961.79
Rate per No. = 25961.79
Say, 25962 .00 each