Item 26.69.4
Considering 1 No. of fixture
(a) 4000 liter stainless steel tank 1 No. @ 40300 each = 40300
(b) Carrying up to site L.S. = 375
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ 180 Per rft. = 180
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ 64.5 each = 64.5
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = 300
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ 300 each = 600
(ii) Skilled labour 4 Nos. @ 200 each = 800
Total = 42619.5
Profit 0.1 = 4261.95
Overhead 0.035 = 1491.68
= 48373.13
Add VAT with adjustment factor 1.04712 0.045 = 2279.36
Grand total = 50652.49
Rate per No. = 50652.49
Say, 50652 .00 each