Item 26.69.5
Considering 1 No. of fixture
(a) 6000 liter stainless steel water tank 1 No. @ 43000 each = 43000
(b) Carrying up to site L.S. = 450
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ 180 Per rft. = 180
(ii) Over-flow 1/2" dia
(iii) G.I. pipe with jum-nuts 1 No. @ 64.5 each = 64.5
(iv) Other small fittings in/c out-let pipe & flange etc. L.S. = 375
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ 300 each = 600
(ii) Skilled labour 4 Nos. @ 200 each = 800
Total = 45469.5
Profit 0.1 = 4546.95
Overhead 0.035 = 1591.43
= 51607.88
Add VAT with adjustment factor 1.04712 0.045 = 2431.78
Grand total = 54039.66
Rate per No. = 54039.66
Say, 54040 .00 each