Item 26.75.2
for single 9" dia size RCC or 300 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3-7" x 3'-7" x 3'-0"= 38.45 cft. @ 1412.5 Per % 0 cft. = 54.31
2. Brick-flat soling:
1 x 3'-5" x 3'-5"= 11.7 sft. @ 1830 Per % sft. = 214.11
3. C.C. (1:3:6) on soling:
1 x 3'-5" x 3'-5" x 0'-3"= 2.92 cft. @ 11182.5 Per % cft. = 326.53
4. C.C. (1:3:6) for invert:
1 x 1'-9" x 1'-9" x 0'-2"= 0.51 cft. @ 11182.5 Per % cft. = 57.03
5. Brick-work (1:6):
2 x (3'-5" + 1'-9") x 2'-6" x 0'-10"= 21.46 cft. @ 8664.25 Per % cft. = 1859.35
6. 12 mm plaster with n.c.f.:
4 x (1'-9" x 2'-6") + 1'-9" x 1'-9"= 20.56 sft. @ 1358 Per % sft. = 279.2
7. Extra labour for making invert & side back-filling:
a) Plumber 0.125 No. @ 300 each = 37.5
b) Skilled labour 0.2 No. @ 200 each = 40
c) Ordinary labour 0.235 No. @ 150 each = 35.25
Total = 2903.28
Profit 0.1 = 290.33
Overhead 0.035 = 101.61
= 3295.22
Add VAT with adjustment factor 1.04712 0.045 = 155.27
Grand total = 3450.49
Rate per No. = 3450.49
Say, 3450 .00 each