Item 26.75.3
for single 12" dia size RCC or 375 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3'-11" x 3'-11" x 3'-3"= 49.94 cft. @ 1412.5 Per % 0 cft. = 70.54
2. Brick-flat soling:
1 x 3'-8" x 3'-8"= 13.47 sft. @ 1830 Per % sft. = 246.5
3. C.C. (1:3:6) on soling:
1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft. @ 11182.5 Per % cft. = 376.85
4. C.C. (1:3:6) for invert:
1 x 2'-0" x 2'-0" x 0'-2"= 0.67 cft. @ 11182.5 Per % cft. = 74.92
5. Brick-work (1:6):
2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"=
31.19 cft. @ 8664.25 Per % cft. = 2702.38
6. 12 mm plaster with n.c.f.:
4 x (2'-0" x 2'-9") + 2'-6" x 2'-6"= 28.25 sft. @ 1358 Per % sft. = 383.64
7. Extra labour for making invert & side back-filling:
(a) Plumber 0.14 No. @ 300 each = 42
(b) Skilled labour 0.23 No. @ 200 each = 46
(c) Ordinary labour 0.27 No. @ 150 each = 40.5
Total = 3983.33
Profit 0.1 = 398.33
Overhead 0.035 = 139.42
= 4521.08
Add VAT with adjustment factor 1.04712 0.045 = 213.04
Grand total = 4734.12
Rate per No. = 4734.12
Say, 4734 .00 each