Item 26.76.2
Considering 1 No. pit cover
1. R.C.C. (1:2:4) for slab:
1 x 3'-5" x 3'-5" x 0'-3" = 2.92 cft. @ 13390.5 Per % cft. = 391
2. 1% re-inforcement in/c fabrication 14.31 Ibs. @ 31.82 Per Ibs. = 455.34
3. 12 mm plaster with n.c.f.:
4 x 3'-5" x 0'-3" + 3'-5" x 3'-5" = 15.12 sft. @ 1358 Per % sft. = 205.33
4. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ 150 each = 15
Total = 1066.67
Profit 0.1 = 106.67
Overhead 0.035 = 37.33
= 1210.67
Add VAT with adjustment factor 1.04712 0.045 = 57.05
Grand total = 1267.72
Rate per No. = 1267.72
Say, 1268 .00 each