Item 26.77.2
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.48 cft. @ 13390.5 Per % cft. = 332.08
2. 1% re-inforcement in/c fabrication 12.15 Ibs. @ 31.82 Per Ibs. = 386.61
3. 12 mm plaster with n.c.f.:
4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") =
13.35 sft. @ 1358 Per % sft. = 181.29
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ 563 each = 563
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ 150 each = 15
Total = 1477.98
Profit 0.1 = 147.8
Overhead 0.035 = 51.73
= 1677.51
Add VAT with adjustment factor 1.04712 0.045 = 79.04
Grand total = 1756.55
Rate per No. = 1756.55
Say, 1757 .00 each