Item 26.77.3
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-8" x 3'-8"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.93 cft. @ 13390.5 Per % cft. = 392.34
2. 1% re-inforcement in/c fabrication 14.36 Ibs. @ 31.82 Per Ibs. = 456.94
3. 12 mm plaster with n.c.f.:
4 x (3'-8" x 0'-3" + 3'-8" x 3'-8" - 0.785 x 1'-6" x 1'-6") =
15.37 sft. @ 1358 Per % sft. = 208.72
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ 563 each = 563
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ 150 each = 15
Total = 1636
Profit 0.1 = 163.6
Overhead 0.035 = 57.26
= 1856.86
Add VAT with adjustment factor 1.04712 0.045 = 87.5
Grand total = 1944.36
Rate per No. = 1944.36
Say, 1944 .00 each