Item 26.80.2
Considering 1 No. soak-well
1. Earth-work: 699 cft. @ 1412.5 Per % 0 cft. = 987.34
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 13.51 cft. @ 13390.5 Per % cft. = 1809.06
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 104.18 cft. @ 7587.28 Per % cft. = 7904.43
4. 10" solid brick-work (1:6) 107.66 cft. @ 8664.25 Per % cft. = 9327.93
5. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of re-inforcement) 9.86 cft. @ 13390.5 Per % cft. = 1320.3
6. 40 grade reinforcement &
fabrication 1.25% 143.14 Ibs. @ 31.82 Per Ibs. = 4554.71
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ 563 each = 563
8. Supply and filling graded
khoa and sand. 251 cft. @ 54.03 Per cft. = 13561.53
Total = 40028.3
Profit 0.1 = 4002.83
Overhead 0.035 = 1400.99
= 45432.12
Add VAT with adjustment factor 1.04712 0.045 = 2140.78
Grand total = 47572.9
Rate per No. = 47572.9
Say, 47573 .00 each