Item 26.81.1
26.81.2 Soak-well for 20 users
Considering 1 No. soak-well
1. Earth-work: 525.02 cft. @ 1412.5 Per % 0 cft. = 741.59
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 10.98 cft. @ 13390.5 Per % cft. = 1470.28
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 84.68 cft. @ 7587.28 Per % cft. = 6424.91
4. 10" solid brick-work (1:6) 87.45 cft. @ 8664.25 Per % cft. = 7576.89
5. R.C.C. (1:2:4) in curb well with 1.5% re-inforcement
(excluding cost of reinforcement) 6.92 cft. @ 13390.5 Per % cft. = 926.62
6. 40 grade reinforcement &
fabrication 1.25% 109.64 Ibs. @ 31.82 Per Ibs. = 3488.74
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ 563 each = 563
8. Supply and filling graded
khoa and sand. 144.24 cft. @ 54.03 Per cft. = 7793.29
Total = 28985.32
Profit 0.1 = 2898.53
Overhead 0.035 = 1014.49
= 32898.34
Add VAT with adjustment factor 1.04712 0.045 = 1550.18
Grand total = 34448.52
Rate per No. = 34448.52
Say, 34449 .00 each