Item 26.84
Punching / cutting hole in RCC floor for sanitary works
Break-up for 6" dia 1 hole
1. Skilled labour 1 Nos. @ 200 each = 200
2. Ordinary labour 0.5 Nos. @ 150 each = 75
3. Tools and plant, sundries etc. L.S. = 12.5
4. Mending good the damages L.S. = 71.43
358.93
Profit 0.1 = 35.89
Overhead 0.035 = 12.56
= 407.38
Add VAT with adjustment factor 1.04712 0.045 = 19.2
Grand total = 426.58
Say 427 .00 Per hole