Item 26.9.2
Considering 1 No. of fixture
1. Coloured wash-basin 1 No. @ 1200 each = 1200
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ 50 each = 50
(b) Grating with brass coupling 1 No. @ 200 each = 200
(c) CP chain with rubber plug 1 No. @ 25 each = 25
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ 370 Per bag = 3.7
(ii) Sand (F.M. 1.2) 0.05 cft. @ 1300 Per % cft. = 0.65
(b) CI brakets 1 Pair @ 65 Per pair = 65
4. Labour:
(a) Plumber 0.15 No. @ 300 each = 45
(b) Skilled labour 0.2 No. @ 200 each = 40
(c) Ordinary labour 0.4 No. @ 150 each = 60
Total = 1689.35
Profit 0.1 = 168.94
Overhead 0.035 = 59.13
= 1917.42
Add VAT with adjustment factor 1.04712 0.045 = 90.35
Grand total = 2007.77
Rate per No. = 2007.77
Say, 2008 .00 each