Item 26.9.3
1. Considering 1 No. of fixture
2. Special coloured wash-basin 1 No. @ 1300 each = 1300
(a) Accessories:
(b) 32 mm dia PVC waste pipe 1 No. @ 50 each = 50
(c) Grating with brass coupling 1 No. @ 200 each = 200
(d) CP chain with rubber plug 1 No. @ 25 each = 25
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ 370 Per bag = 3.7
(ii) Sand (F.M. 1.2) 0.05 cft. @ 1300 Per % cft. = 0.65
(b) CI brakets 1 Pair @ 65 Per pair = 65
4. Labour:
(a) Plumber 0.15 No. @ 300 each = 45
(b) Skilled labour 0.2 No. @ 200 each = 40
(c) Ordinary labour 0.4 No. @ 150 each = 60
Total = 1789.35
Profit 0.1 = 178.94
Overhead 0.035 = 62.63
= 2030.92
Add VAT with adjustment factor 1.04712 0.045 = 95.7
Grand total = 2126.62
Rate per No. = 2126.62
Say, 2127 .00 each