Item 27.16
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ 350 each = 350
(b) Skilled labour 4 Nos. @ 200 each = 800
(c) Local carriage, T & P L.S. = 112.5
Total = 1262.5
Profit 0.1 = 126.25
Overhead 0.035 = 44.19
= 1432.94
Add VAT with adjustment factor 1.04712 0.045 = 67.52
Grand total = 1500.46
Rate per rm. = 15
Say, 15 .00 Per rm.